📉 Project Budget Analyzer

Metro Blue Line Phase 3 QA/QC Program · Contract Value: $8,200,000 · Crestline Construction Management

WBS Budget Breakdown — As of April 30, 2026 (Month 14 of 36)
WBS Code Description Approved Budget Actual Spent % Complete Variance Status
1.1.0 Project Management & Administration $480,000 $212,400 38.9% +$267,600 ON TRACK
1.2.0 QA/QC Inspection Services — Civil $1,640,000 $921,400 42.1% +$718,600 ON TRACK
1.3.0 Structural Inspection & Testing $1,120,000 $748,300 56.8% -$124,300 WATCH
1.4.0 Materials Testing Laboratory $620,000 $491,200 63.4% -$185,200 OVER BUDGET
1.5.0 Environmental Compliance Monitoring $840,000 $298,100 34.2% +$541,900 ON TRACK
1.6.0 Document Control & Reporting $380,000 $281,600 61.7% -$96,400 WATCH
1.7.0 Special Inspections (IBC Chapter 17) $960,000 $712,800 67.2% -$238,200 OVER BUDGET
1.8.0 Subcontractor QA Oversight $460,000 $148,900 29.8% +$311,100 ON TRACK
TOTAL PROJECT $6,500,000 $3,814,700 46.3% -$86,400 net WATCH
Note: $1,700,000 in contingency and management reserve not shown above. Remaining contract ceiling: $8,200,000.
AI analyzing budget variances and generating corrective actions...
72
Project Health Score: 72/100
CAUTION — Two WBS items significantly over budget relative to percent complete. Corrective action recommended within 30 days.