Raw Project Notes — March 2026
UNFORMATTEDMetro Blue Line Phase 3 — March notes
Submittals:
- reviewed 34 submittals this month, approved 28, returned 6 with comments
- concrete mix design finally approved after 2 resubmittals
- MEP electrical submittal 06-E-014 still pending (overdue 12 days)
NCRs:
- opened 4 new NCRs in March
- NCR-B-038: formwork gap station A, closed 3/12
- NCR-B-039: concrete placement in rain, closed 3/19
- NCR-B-040: rebar coupler installation, open, waiting on contractor RFI
- NCR-B-041 opened 4/29 (April, not March)
Safety:
- had 3 safety meetings
- one near-miss incident 3/14 at station B — worker on scaffold without proper tie-off, corrective action issued same day
- no recordable incidents
- safety rep Eduardo reviewed site 3/21
Schedule:
- 3 days behind baseline on excavation due to utility relocation
- foundation work on track now
- overall project: on schedule per last update
Issues/Risks:
- SoCal Gas permit delayed - still waiting
- MEP submittal backlog is getting worse
- Skanska has been slow to respond to RFIs - averaging 9 days (spec says 7)
Budget: nothing major, CO-047 still pending, all else within contingency
AI-Generated Monthly Status Report
AI FORMATTED
📋
Click "Generate Monthly Report" to transform the raw notes into a polished, executive-ready status report.
⚡ Report ready in 58 seconds
Executive Summary
Progress This Period
Issues & Risks
NCR Summary — March 2026
| NCR No. | Description | Date | Status |
|---|---|---|---|
| NCR-B-038 | Formwork gap — Station A | Mar 5 | CLOSED 3/12 |
| NCR-B-039 | Concrete placement during rain event | Mar 15 | CLOSED 3/19 |
| NCR-B-040 | Rebar coupler installation nonconformance | Mar 22 | OPEN |