RFI Response

Draft RFI responses against your spec library — with the citations included.

–65%time per RFI
Purely Works × ❓ RFI Response AI
← Demo Center Book a Call

❓ RFI Response AI

Draft professional, technically accurate RFI responses in seconds — with proper contract citations

Incoming RFI — From Walsh Construction
#0234
April 28, 2026
May 5, 2026
URGENT
Walsh Construction — Dave Park, Supt.
Crestline CM — Eduardo Martinez
03.30.00
Station C — Retaining Wall Footings
QUESTION FROM CONTRACTOR:
"Please clarify the concrete compressive strength requirement for the retaining wall footings at Station C. The structural drawings (Sheet S-14, Detail 4/S-14) indicate f'c = 4,000 psi for all footing elements. However, Specification Section 03.30.00, Paragraph 2.1.3 specifically calls for f'c = 5,000 psi for all below-grade structural concrete applications. The two documents conflict. Which governs, and is there a cost/schedule impact?"
Spec Reference — Section 03.30.00, Para 2.1.3
"All below-grade structural concrete, including but not limited to footings, pile caps, grade beams, and retaining walls, shall achieve a minimum compressive strength of f'c = 5,000 psi at 28 days. This requirement supersedes any drawings notation that may indicate a lesser strength for below-grade elements."
Drawing Reference — Sheet S-14, Detail 4/S-14
"Retaining Wall Footing — f'c = 4000 psi, 3" clear cover, #8 @ 12" E.W. bottom mat. See schedule for reinforcement details."
 AI researching spec hierarchy and drafting formal response...
✓ Response drafted in 41 seconds — vs. 1-2 hours for manual review

RFI RESPONSE — #0234

Metro Blue Line Phase 3 QA/QC Program  ·  Contract No. PSA-24-3182  ·  Crestline Construction Management